France’s Flamanville 3 nuclear reactor, its most powerful at 1,600 MW, was connected to the grid on December 21 after 17 years of construction plagued by delays and budget overruns.

The European Pressurized Reactor (EPR), designed to boost nuclear energy post-Chernobyl, is 12 years behind schedule and cost €13.2 billion, quadruple initial estimates.

President Macron hailed the launch as a key step for low-carbon energy and energy security.

Nuclear power, which supplies 60% of France’s electricity, is central to Macron’s plan for a “nuclear renaissance.”

  • etuomaala
    link
    fedilink
    English
    arrow-up
    1
    ·
    18 hours ago

    Extracting its latent energy value in a cost-effective manner remains a challenge, and will require considerable R&D investment.

    The physics are sound. It’s the economics that are apparently still a problem.