Hi everyone!

A slow week went by, with daily heavy rains it’s not always easy to find the motivation to work outside.

We installed a 50 square meter fleece and pond liner on top of the build, and started backfilling with dirt.

It’s a lot of work because we have to dig the overgrown pile of dirt that’s been sitting for 5 years on our lot, first getting rid of the roots in the top soil. But we have to do this manually as the back is only reachable through a narrow path in our neighbor’s garden.

My partner also installed the electrical panel with 24V circuits for RGBW LED strips, a PoE WiFi access point and connected the wall outlets to the 230V main. It was temporarily connected to test how bright the strips will be. They will later be mounted in metal railings across the whole length of the lower brick line, with a wood cladding.

We will then have to dig a 20 meter trench from the house main electric supply, lay a PVC pipe and pull a 3-phase copper line to the cellar. This will be the garden hub to provide electricity to the future outdoor kitchen.

The next few days we will work on the mortar joints, using the multitool diamond blades that arrived in the mail to finish the cleanup before grouting all the joints cleanly.

Have a great week and keep on doing it yourself!

  • rbn
    link
    fedilink
    arrow-up
    4
    ·
    edit-2
    1 month ago

    Really cool project! But you really missed the chance to integrate a tiny hidden runnel right into your house to sneak in and out.

    (Or you hid it really well ;))

    • morgunkorn@discuss.tchncs.deOP
      link
      fedilink
      arrow-up
      3
      ·
      1 month ago

      haha yeah, no way to sneak in secretly to gurgle a bottle of wine ^^

      the house is wood frame on concrete slab, it’s gonna be difficult to connect both buildings together